The Outer Ring road will be completed by April 2018, Kenya Urban Roads Authority has said.
The Sh9.3 billion project was to be completed this month but Kura says it is currently 87 per cent done.
General director Silas Kinoti said on Monday that outstanding works include footbridges, streetlights, landscaping and construction of sectors of service roads.
“The contractor is set to start works on the footbridges in January and to be completed by April 2018,” Kinoti said in a statement.
He added that construction of a fresh produce market at Kangundo Road Junction is on going.